work | status | planned dates |
---|---|---|
move gpu001...gpu010 to rack 100 | TBD - 1952 | 2013-12-09 |
move gpu011...gpu020 to rack 101 | TBD - 1953 | 2013-12-09 |
move gpu021...gpu030 to rack 102 | TBD - 1954 | 2013-12-09 |
move gpu031...gpuXXX to rack 102 filling holes | TBD - 1955 | 2013-12-09 |
install old radio switch into rack D | TBD - 1956 | 2013-12-09 |
cable and configure two radio switches in rack D | TBD - 1957 | 2013-12-09 |
move E@H build machines to new location (rack 79 or I) | TBD - 1958 | ??? |
move gpuXXX...gpu040 to rack 5 | TBD - 1959 | 2013-12-10 |
move gpu041...gpu050 to rack 6 | TBD - 1960 | 2013-12-10 |
move gpu041...gpu050 to rack 6 | TBD - 1961 | 2013-12-10 |
install new infrastructure servers into rack 25 | TBD - 1962 | ??? |
cable new FS500 switches in racks H and I | TBD - 1963 | 2013-12-10 |
install and cable new FS100 switches in racks 51...56 | TBD - 1964 | 2013-12-10 |