Infrastructure work at the end of 2013

work status planned dates
move gpu001...gpu010 to rack 100 TBD - 1952 2013-12-09
move gpu011...gpu020 to rack 101 TBD - 1953 2013-12-09
move gpu021...gpu030 to rack 102 TBD - 1954 2013-12-09
move gpu031...gpuXXX to rack 102 filling holes TBD - 1955 2013-12-09
install old radio switch into rack D TBD - 1956 2013-12-09
cable and configure two radio switches in rack D TBD - 1957 2013-12-09
move E@H build machines to new location (rack 79 or I) TBD - 1958 ???
move gpuXXX...gpu040 to rack 5 TBD - 1959 2013-12-10
move gpu041...gpu050 to rack 6 TBD - 1960 2013-12-10
move gpu041...gpu050 to rack 6 TBD - 1961 2013-12-10
install new infrastructure servers into rack 25 TBD - 1962 ???
cable new FS500 switches in racks H and I TBD - 1963 2013-12-10
install and cable new FS100 switches in racks 51...56 TBD - 1964 2013-12-10

-- CarstenAulbert - 09 Dec 2013
Topic revision: r1 - 09 Dec 2013, CarstenAulbert
This site is powered by FoswikiCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding Foswiki? Send feedback